TL;DR
Wallonia ordered Google to suspend construction at its planned Farciennes data centre, saying a three-hectare building lacked proper planning permission. The dispute is linked to a rejected application to use water from the River Sambre for cooling; Google has challenged that refusal, with a court hearing scheduled for January.
Wallonia’s regional authorities have ordered Google to stop construction on a building at its planned Farciennes data centre, saying a three-hectare structure was built without proper planning permission. Google says work is paused while it awaits further guidance. The order puts part of a major technology project on hold amid a dispute over both construction permits and a proposed plan to draw cooling water from the nearby River Sambre.
Regional officials said inspectors visited the site on Thursday and instructed Google representatives to halt work. Nicolas Yernaux, a spokesman for Wallonia’s authorities, described the building as an alleged “major offense” because it was constructed without the required permission, according to AFP. The regional order concerns one building, not the entire site.
The building covers about three hectares, while the former mining property earmarked for the data centre spans roughly 50 hectares, AFP reported. The project initially planned to use air cooling, according to Belgian media cited by AFP. Google later sought permission to change the system and draw water from the Sambre. Regional authorities rejected that request over the summer, amid concerns about water use during severe drought conditions reported since spring.
Greenpeace Belgium said in a report this week that drone footage showed construction continuing, and alleged that Google was working after the latest version of its planning permission had been revoked in August. Those are claims by the environmental group, not findings by a court. Google told the BBC it had paused the work “pending additional guidance” and said it remains committed to complying with local laws. The company has challenged the refusal of its permit application in court.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Permits Put Data Centre Plans at Risk
The order shows how local planning decisions can delay data centre construction even as technology companies seek more capacity for cloud computing and artificial intelligence. For Google, the immediate issue is a halt affecting a building within the Farciennes project; the available reports do not establish that all work across the wider site has stopped.
The water dispute also points to a practical constraint on projects: cooling systems need resources, and proposed withdrawals can face scrutiny where drought has raised concerns. Reports do not state how much water Google’s proposed system would use, so the scale of the project’s potential demand cannot be determined from the information available.
Delays can affect construction schedules and plans to add computing capacity, but the consequences for Google’s services, customers or project costs have not been reported. More broadly, the case illustrates how access to land, power and water, as well as permits, can shape where data centres are built and when they become operational.
Popular right now

Ninja Foodi Power Blender & Processor System, 7 Functions, Silver, SS401

Dyson Airwrap Multi-Styler Complete Long

Hisense E7 Cinema Series 65-Inch Hi-QLED Mini-LED 4K UHD Smart Fire TV
As an affiliate, we earn on qualifying purchases.
How the Farciennes Dispute Developed
The planned data centre is on a former mining site in Farciennes, in southern Belgium. The project had been planned with air cooling, but Google applied to change the arrangement to water cooling using the nearby Sambre. Authorities rejected the requested change over the summer. Reports link the opposition to concerns about taking water from the river during a period of drought.
Greenpeace Belgium subsequently alleged that construction continued despite the planning issue. Following a site visit, regional officials ordered the halt and cited the building’s size and lack of proper permission. The order and the authorities’ explanation have been reported through statements to AFP and the BBC; the source material says the text of the order itself could not be found online.
The dispute comes amid wider scrutiny of data centre development. AFP reported that Finnish authorities halted work at two Google data centre sites in October. That is a separate case and does not establish the outcome of the Belgian dispute. The BBC reported that Belgium has 54 data centres, citing Data Center Map; the figure provides national context but does not indicate the size or status of Google’s project.
“We have operated in Belgium for over 15 years and remain committed to complying with local laws.”
— Google, in a statement reported by the BBC
The Permit Case Is Still Open
The legal dispute has not been resolved. Google has challenged the authorities’ refusal of its water-cooling application, and a hearing is scheduled for January, but the source reports do not give the court’s eventual timetable or outcome. It is also unclear whether the company will seek to revise its plans or apply for another permit.
The exact scope and terms of the stop-work order remain difficult to verify because the order itself was not found online in the cited reporting. Officials say the three-hectare building lacked proper permission; Greenpeace alleges construction continued after the latest permission was revoked. The available material does not establish whether the building can later be legalised or what corrective steps authorities would require.
There is no reported figure for the amount of Sambre water the proposed cooling system would use, nor a confirmed schedule for the broader site. Google says work is paused, but the reports do not clarify whether any other activities at the property may continue.
January Hearing Will Test the Permit
The next reported milestone is the court hearing scheduled for January on Google’s challenge to the refusal of its permit application. The hearing may clarify the legal status of the proposed water-cooling plan, although the reports do not say whether it will decide the separate question of the building cited in the stop-work order.
Until then, Google says construction is paused pending further guidance. The regional authorities’ order remains in effect according to the available reporting. Any decision on revised permits, the building’s future or a possible restart of work has not yet been announced.
Key Questions
Why did Wallonia order Google to stop construction?
Regional authorities said a three-hectare building at the Farciennes site was constructed without proper planning permission. Inspectors visited the site and told Google representatives to halt work, according to the authorities.
What is the dispute over the River Sambre?
Google sought to change the project’s cooling plan from air cooling to a system using water from the River Sambre. Authorities rejected the application over the summer amid reported concerns about water use during drought conditions. The proposed volume of water has not been reported.
Has Google stopped all work at the Farciennes site?
Google told the BBC that it had paused works pending additional guidance. The reported order concerns one building, not the entire 50-hectare property, and reports do not specify whether other site activities can continue.
What happens next in the dispute?
Google has challenged the refusal of its permit application, with a court hearing scheduled for January. The outcome and any further permitting steps have not been reported.
Source: ThorstenMeyerAI.com